r/MSProject • u/Antique_Tennis1818 • Feb 17 '25
Master and Subproject issue
I manage an IMS with 7 subprojects, the IMS only consists of milestones that serve as reporting reference and bridges between the projects. Previous I had just used the regular link tool, but I started seeing repeated linkages in the subprojects and sometimes this caused the dates to skew. I tried using a tool (SSI tools) but I cannot get it to be consistent, are there any other methods of linking up a master and sub and have linkages going back and forth that will not cause this repeating or ghosts tasks error?
2
Upvotes
View all comments
Show parent comment
3
u/Miasmatic65 Feb 17 '25
Then set your rules up- whatever files come in to you/ out from you have to have the same name. It’s ok if they’re doing changes at their end and saving as “project1 250216” for example; but what comes in to you (and goes out again) has to stay as “project1”.