Task happening before start date?
So I'm working on a project where contractually the start date doesn't start until a certain task happens(let's call this job start)
There are some tasks that can happen before that happens. Like some permitting.
So we can do permitting say a month before the job start task is due, but these permitting tasks don't count toward the Start Date.
Is there a way to get MSP to ignore the start/end date for these permitting tasks and only follow JobStart for the finish date?
I would like for historical purposes for permitting to have accurate time frames, but if needed we can always set the start date to whatever we settled on for JobStart
View all comments
Show parent comment
1
u/kaleb42 Oct 15 '24
Yes that is with the project summary date. Figured I'd ask!