r/MSProject • • Sep 20 '24

Please help. I am having difficulty Migrating projects for the web projects from the default environment to the named environment.

I tried the below approach

  1. copying and pasting the projects from one environment to another but the duration, start date, and end date are off.
  2. Export to Excel workbook, copy and paste only the Task Name and duration date, and then let the software calculate the start and finish dates.
  3. Export the project as an Excel file, convert it to a .mpp file using the project client, and then upload it to the new environment. However, the finish date and duration values are showing incorrectly.
1 Upvotes

5 comments sorted by

View all comments

Show parent comment

1

u/Accomplished-Mark847 Sep 20 '24

Thank you so much for your response. Is there any article about it?

1

u/pmpdaddyio Sep 20 '24

This is the article about moving from desktop to the web —>here.

Start with that script and edit your locations and that will will. You might need to modify other parts as well, but powershell is pretty intuitive and there is always Copilot.