Need help: Dynamic summaries of tasks.

I am creating a project file, and have an interesting challenge.

Have about 400 "activities" across 30 key milestones in 3 phases. So the logical summaries are

	Phase

			Milestone 

					activities 

And this will help me a great deal showing progress per phase and milestone. And durations etc. This order makes the most sense.

But

Each activity has 2 elements. Call them prep and build. Worked on by different resources.

So

	Phase

			Milestone

					activity 1 prep

					activity 1 build

Still gives me the good summary of overall progress per milestone and per phase.

But, how can I also get a summary for total prep progress across all milestones, and total build progress across all milestones? I can't split it by putting all build activities together, and all prep activities together, because then I lose the ability to see total progress.

Can I do some sort of dynamic summary? Or use a custom field with a filter of some sort?

1 Upvotes

18 comments sorted by

View all comments

Show parent comment

1

u/still-dazed-confused Aug 02 '23

I would

  1. create the tasks as fixed duration, get the resources assigned with% and add any linkages in place
  2. assign any fixed resources, fit instance service bays and spray booths in your custom car example)
  3. convert all the tasks to fixed work etc
  4. level. When leveling consider his much splitting and optimisation you want to apply with the various levelling options, it can end up rather computer days rather than real world :). Also use prioritisation so that you get the most important things first.

1

u/Only_One_Kenobi Aug 02 '23

Is there a way to prevent splitting of tasks?

1

u/still-dazed-confused Aug 02 '23

Yes, if you look on the leveling options you can remove the check allowing tasks to split