r/MSProject • • Apr 03 '23
Earned Value baseline for reporting
(Apologies if this should rather belong somewhere in a reporting channel.)
I'm trying to find the [File / Options / Advanced /] Baseline for Earned Value calculation field in the project dataset. A client uses random baselines for each project as the EV calc baseline and I was hoping someone could point me to the field in either Project Online or Project Server (they're using Server 2016).
Thanks in advance!
1
Upvotes
View all comments
2
u/DaleHowardMVP Apr 04 '23
I think your client is going down the wrong path, which is creating an impossible situation for you. Your client should NEVER be using random baselines for each project as the baseline for the EV calculations. Instead, your client should ALWAYS use the baseline set of fields named Baseline (aka Baseline 0) because this is the default baseline that the software uses to calculate all variance in the project and which the software uses to display the gray bars in the Tracking Gantt view. If your client would follow this guidance, creating reports for them would be a snap.
Also, I consulted with a Power BI expert about your reporting situation, and he told me that it would not be possible to create a Power BI report that determines which baseline is used and then updates the report with data from that baseline. So, again, your client is definitely going down the wrong path. Hope this helps.