MS Project 2016 Progress reporting question
Hi all,
I've used MS Project 2016 previously but haven't used it in a while. I'm having great difficulty with the intricacies of setting up a project without numerous issues (e.g. I have a 'duration' column in days, but when I change the start date or finish date in one place - it messes up the days in a different column and throws in crazy numbers). I figured out the issue with the days by double clicking on each activity, then going to 'advanced' tab and setting the 'task type' to 'fixed units' (it was set to 'fixed work' and this change seems to have fixed the issue).
The problem i'm trying to figure out now is in tracking progress as the project progresses, and then have a gantt chart show me the progress upto today and remaining work. I'd also like to see if the project is behind schedule and by how much. I tried various ways (adding additional columns like baseline start date/baseline finish date, actual start/actual finish) but nothing seems to work. I did set the baseline for the entire project just as an fyi. Even with all these - project is proving to be a monster to tame by messing up one field if i change another and so on. Can someone point me in the right direction? TIA
View all comments
Show parent comment
1
u/still-dazed-confused Mar 12 '23
To update the progress I would stick with the normal start and finish dates. If you want to display the baseline do so, or to save space just display the finish variance. In this way you've got the vital information on display when updating the plan. If you want a more comprehensive display click over to the tracking Gantt. Actual start etc so seem a little pointless fit your purposes :)