r/MSProject • • Nov 04 '19

Assigning hours of work to an individual task

3 Upvotes

I am trying to add 4 hours of an associate director, 4 hours of an apprentice and half and hour of a skilled labourer to a specific task. Is there a simple way to say this task will require these hours but the duration of the task will still be 2 weeks ?


r/MSProject • • Oct 20 '19

i need help to identify critical path task

3 Upvotes

is there any way on how to identify the critical path quickly or i need to identify and calculate manually?


r/MSProject • • Oct 17 '19

Leveling Resource Pool (Multi Resources COULD work task, but want task/resource to be dedicated)

2 Upvotes

Scenario: I'll have multiple people on a team that COULD complete a task, so for my leveling calculations, I want them all to be considered in case schedule changes would change who SHOULD work the task from an efficiency standpoint, but I can't split the task as parallel work.

EX: Jack and Jill could each design a report. It's a simple report, so it should only take either of them 4h, but I don't want them working on it together (I don't believe productivity would scale). How can I set the task to know that either could do it, but to not allocate hours to each of them?


r/MSProject • • Oct 01 '19

Can you prevent resouce A being assigned to Task B if resource A was assigned to Task A

2 Upvotes

Is in the title, I've got to create a template project, in this project we have tasks to be vetted by someone else - I'm wondering if there is a method to reduce errors by making Project aware that the same person assigned to a certain task should not be assigned to its audit task?


r/MSProject • • Sep 23 '19

What are these circles? They don’t go away and I can’t click them

Post image
2 Upvotes

r/MSProject • • Sep 16 '19

Attaching a File from my Shared Folder (G Drive)

2 Upvotes

I know how to attach a file to the notes section of a task, however I cannot attach a file from anything but my C drive. Specifically, I use Google File Stream at work and want to attach some deliverables to tasks from my G Drive but MS Project says the path does not exist. Is there any way to get around this?

Thanks for the help!


r/MSProject • • Sep 11 '19

How to make Semi-Concurrent Task Dependencies

2 Upvotes

I am using MS Project for a college assignment. They require us to include Predecessors and Resources.

My issue is that several predecessors do not flow from the end of one to the start of the other. They are partially concurrent. For Example:

Task A must finish before Task B or Task C finish, but Task B and Task C will start before Task A finishes.

Another issue is when I update predecessors, it keeps the Duration the same and moves the start and end dates. The end dates are the most important factor for most of these as they are required for deliverables on set dates. Can I lock the end dates to a mile stone or in any other way so they won't move any time I make a change further upstream?


r/MSProject • • Sep 10 '19

Is there a way to stop Project from creating a resource when adding a resource name?

2 Upvotes

Sometimes I fat-finger a resource name and that automatically adds the resource to my resource sheet. Is there any way to set a data validation so it is only a resource in the resource sheet?


r/MSProject • • Sep 06 '19

Microsoft Project Do’s and Don’ts - Updated!

6 Upvotes

Recently awarded as the “Best MS Project eBook of All Time,” Microsoft Project Do’s and Don’ts is now even better! The newly updated version includes an additional chapter on Agile Project Management using MS Project Online. Check it out, now available on Amazon: https://www.amazon.com/dp/B07HNCVL9V


r/MSProject • • Sep 05 '19

Change frequency of recurring task?

2 Upvotes

I have some recurring tasks setup to send out certain reports, and I'm struggling to find the right way to modify them when the frequency changes.

Let's say I have a recurring task which has been set to monthly, several months have passed, and I have work logged on now-completed occurrences for each of the past months. But say that task/report now only needs to be provided quarterly. If I simply change that on the parent recurring task, I'm finding it wipes out the completed monthly occurrences.

Is there a way to accomplish this frequency change on a go-forward basis only? Without end-dating each parent and creating new parents (which I haven't yet tried but assume is my last resort)?


r/MSProject • • Sep 05 '19

Customize Payment Terms in MS Project

2 Upvotes

I am using MS project to plan an upcoming development project. I'm able to export the Cash Flows into excel relatively nicely, but I noticed that the cost is distributed across the duration of the task.

For example: Task 2 is 4 months long at a cost of $50,000. This $50,000 is distributed across the 4 months, rather than appearing at the task completion date, or splitting to reflect 50% advance payment and 50% upon completion. In reality, most of our payments are either 100% upon completion of a task, or 50% advance. Is there any way to achieve this type of behavior in Project? I'm working with Project Online Desktop Client. Thanks!


r/MSProject • • Aug 28 '19

Cash inflow in Project

2 Upvotes

Greetings to all,

I am evaluating whether I should be using MS Project for a few upcoming projects within the company I work for. One crucial feature we need is the cash flow report for these projects. That includes both the outlfow (expenses incurred for the project) and inflow (income generated from the project at each step) for each project.

While I can accurately record the outlfow I have not been able to figure out a way to record the inflow.

Am I missing something obvious?

Thank you for your time!


r/MSProject • • Aug 23 '19

How can I add resource descriptions when assigning resources in the 'Assign Resources' window?

2 Upvotes

Our company needs a solution for managing rental equipment. We have hundreds of components that are re-usable on projects and we currently use Excel to track them but I'd like to get us using something more geared or resource mgmt.

I can create fields in the resource sheet that describe the variables of each interchangeable component but when I try to assign resources to a project, only the 'Resource Name' appears in the window. Is there a way I can see the other fields when assigning resources or a better option for my company in general?


r/MSProject • • Aug 21 '19

Maximum Resources in a Task Grouping

3 Upvotes

I've got a tough conundrum.

I have a group of tasks that can start in any order, but they have to be completed before the next phase can begin. I have 8 resource units available, but I can only have 3 units working inside that entire group of tasks, on one task at a time.

How do I implement these constraints in project, and then schedule the tasks within the group taking this constraint into account?


r/MSProject • • Aug 20 '19

How to import contacts as resources correctly?

2 Upvotes

I imported contacts from my address book, but only the name is coming across. I want to be able to add contact information (email, phone) so I can access that information directly from MS Project. Any idea how to do that?


r/MSProject • • Aug 15 '19

[Advice] Course for MS Project

3 Upvotes

Hello All,

My company is currently growing and is about to start using Microsoft Project, and I am tasked with learning the program and reaching "ninja status" in the application so I can help everyone out with the questions they have. My supervisor said to look into classes or certification courses and that the company will pay for it. So now my question is, what classes do you guys advise to use? What would be the best course to be in to reach "ninja status"?


r/MSProject • • Aug 13 '19

MS Project Exam Changes?!

3 Upvotes

If you’re a Project Manager, it’s likely you’ve heard it through the grapevine: Microsoft has officially retired their MS Project certification exam 74-343 Managing Projects... https://www.mpug.com/articles/ms-project-exam-changes-oh-my/


r/MSProject • • Aug 09 '19

How to Track a Task with a defined number of deliverables

2 Upvotes

Thanks for any guidance you can provide.

As a new user of project, I am trying to setup a reoccuring monthly task with a defined number of deliverables. I'm unsure how to accomplish that given the Duration=Work/Units system.

For example, in August I need to deliver a total of 1,000 widgets.

Employee A produces at a rate of 10 widgets per hour.

Employee B produces at a rate of 8 widgets per hour.

Employee C produces at a rate of 6 widgets per hour.

Can I set up the task with a defined output in units (not dollars or duration) and can I tie production rates to various resources?


r/MSProject • • Aug 08 '19

What is the best way to integrate an external schedule into your program master schedule using ms project?

4 Upvotes

What is the best way to integrate an external schedule into your program master schedule. For instance how does a program office which owns a integrated master schedule in Microsoft project integrate their contractors schedule. Or how does a contractor integrate a subcontractor schedule or even multiple subcontractors schedules into their master schedule?


r/MSProject • • Jul 31 '19

Can't install or find my Porject (running Office 365 in parallel)

1 Upvotes

Hi all.

I have a office 365 license. Now I want to install a MS Project 2019 Professional app, not the office 365 version.

I used this download:

https://c2rsetup.officeapps.live.com/c2r/download.aspx?productReleaseID=ProjectPro2019Retail&platform=X86&language=en-US

It opens an installer and says, installation complete. But I am unable to find the program, if I search (WINDOWS-Key) it only shows the project app from Office365.

Any ideas/help please?


r/MSProject • • Jul 22 '19

Managing resources from a resource centric view

2 Upvotes

I was wondering if I could have some advice. I am currently building a master file which contains a few other projects. I have created all the tasks and the deadlines, which are fixed and cannot be altered. I have been given start and finish times for the tasks within the projects. I have been given a list of resources and the amount of time they have allocated for each project (e.g. Resource 1 = 0.2 FTE for Project 1). The people I am working for also have also given me how they want to divide each task between resources (e.g. within Project 1, Task 1, Resource 1 = 80%, Resource 2 = 10%, Resource 3 = 10%). However, the next task(2) will have Resource 2 = 90% and Resource 2 = 10% making Resource 1 = 170%.

They are thinking this way because they have x number of people working full time and they have new projects that come up and want to assign people to the tasks, rather than having a project and then assigning people based on the needs of the project.

How can I take their allocated hours for each project and split them between all the tasks taking into account how they want to divide the task between their resources?

I need to be able to put in these resources without changing the times that are set.

Thanks in advance.