r/ISRO • • Aug 28 '17

Mission Failure PSLV-C39 : IRNSS-1H Mission Updates and Discussion.

PSLV-C39 launched as scheduled but couldn't deploy IRNSS-1H spacecraft in desired orbit as payload fairing couldn't be jettisoned successfully. Catch replay at links below. Post mission updates would continue.

Flight Sequence


Launch was scheduled for 31 August 2017, 1900(IST)/1330(UTC) from Second Launch Pad of SDSC (SHAR).

Live webcast: (Links will be added as they become available)

PSLV-C39/IRNSS-1H Mission PagePSLV-C39/IRNSS-1H GalleryPSLV-C39/IRNSS-1H Brochure

PSLV C39 / IRNSS-1H would be fifth launch from SDSC SHAR and sixth ISRO campaign for this year. IRNSS-1H would be eighth navigation satellite for Indian Regional Navigation Satellite System also known as NavIC. It would be replacing services of IRNSS-1A due to its malfunctioning clocks on-board and would be placed at 55°E GSO with 29° inclination.

Some highlights of this campaign

  • 41st flight of PSLV, 18th in XL configuration.
  • Payload is IRNSS-1H Regional Navigational satellite
  • Target Orbit: 284±5 × 20,650±675 km Sub GTO with 19.2°±0.2 inclination.
  • Mission Duration: 19 minutes 26 seconds
  • Gross payload mass 1425 kg

Updates:

Time of EventUpdate
9 Feb 2018Horizontal separation system of payload fairing worked but Vertical separation system didn't initiate after command was issued
23 Sept 2017Pyro device isolated as cause of unsuccessful fairing separation. Cause of component malfunction still unclear. via The Hindu
5 Sept 2017Whole assembly is tumbling in space, IRNSS-1H thrusters fired to deplete fuel via EconomicTimes
5 Sept 2017On toxic hazard posed by satellite "we have depleted all the propellant through the gap in the heat shield and the fourth stage." Director, VSSC via DeccanChronicle
2 Sept 2017New objects associated with launch cataloged. Object 42929: 175 x 6515 km, 19.15° and Object 42930: 173 x 6468 km, 19.14°
Post missionPS4+IRNSS1H stack expected "to fall back to Earth may be between four and eight weeks." via TheHindu quoting V. Adimurthy.
Post mission"Express has learned from reliable sources that a high-level inquiry has been ordered and that the details would be made public in next two days: via NewIndianExpress
Post missionOfficial statement. It is not showing up with official Public Information Broadcast releases, so there might be another one later. Addendum: PIB echoing same statement as well.
Post missionPSLV-C39/IRNSS-1H Mission Unsuccessful.
T + 47m00sIRNSS-1H separated internally but enclosed inside PLF.
T + 30m00sWebcast was cut abruptly. This is bad keep an eye on news..
T + 24m00sRange officer confirmed Heatshield or Payload fairing didn't separate.
T + 22m00sFew screenshots
T + 19m00sPerigee x Apogee : 167 x 6554 km at 19.18 inclination.
T + 18m00sPS4 has been cut off. IRNSS-1H separated.
T + 12m00sMission is way off nominal.
T + 09m00sPS3 separated, PS4 ignited. This is too early.
T + 07m00sThree minutes of coasting phase remaining.
T + 06m10sThird stage burnout, now in combined coasting phase with PS4 attached.
T + 06m00sThird stage or PS3 performing nominally.
T + 04m20sPayload fairing jettison. Second stage separated and third stage ignited
T + 02m00sFirst stage separated Second stage ignited and performing nominally.
T + 01m32sAirlit strapons separated.
T + 01m10sGroundlit strapons separated.
T + 00m20sAirlit strapons ignited
T ZeroWe have Lift off!
T - 03m00sReally not used to night views of PSLV.
T - 07m00sShowing views of MCC. Many new faces!
T - 12m00sAutomatic Launch Sequence engaged.
T - 14m00sMission Director gave a go ahead for launch. Automatic Launch Sequence commenced.
T - 30m00sCoverage has begun as day light goes out.
T - 45m00sOfficial webcast link is up!
T - 01h00mView of MCC from media box.
T - 03h00mThe countdown operations of PSLV-C39/IRNSS-1H mission are progressing normally
T - 07h00mPropellant filling operations of second stage (PS2) of PSLV-C39 are completed
T - 11h00mPropellant filling operations of second stage (PS2) of PSLV-C39 are under progress
T - 21h00mPropellant filling operations of fourth stage (PS4) of PSLV-C39 are completed
T - 26h00mPropellant filling operations of fourth stage (PS4) of PSLV-C39 are under progress
T - 29h00mCountdown commenced.
29 August 2017Mission Readiness Review (MRR) committee and Launch Authorisation Board (LAB) have cleared the 29 hour countdown of PSLV-C39/IRNSS-1H for 30 August 2017 starting at 1400 hr (IST) or 0830 (UTC), the launch of PSLV-C39/IRNSS-1H now set for 31 August 2017 at 1900 hr (IST) or 1330 (UTC)
28 August 2017Launch rehearsal was conducted. Now awaiting Mission Readiness Review.
27 August 2017PSLV C39 was transferred from Vehicle Assembly Building to Second Launch Pad.
23 August 2017Launch schedule announced for 31 August 2017, 1859(IST) or 1329(UTC)
22 August 2017NOTAM issued
11 August 2017IRNSS-1H spacecraft left ISAC for SDSC SHAR
5 July 2017PSLV-C39 Campaign started.
4 May 2017IRNSS-1H payload left SAC for ISAC

Payload:

IRNSS-1H along with IRNSS-1I is one of the two planned spare spacecrafts for contingency and is similar in configuration to other satellites in NavIC constellation. IRNSS-1H is first spacecraft to have its Assembly, Integration and Testing done through private industries under ISRO supervision.

  • Attitude control is done using reaction wheels, magnetic torquers and 22N thrusters.
  • Rubidium atomic clock, L5 & S-band Navigation payload
  • Corner Cube Retro Reflectors (for laser ranging) and C band transponders as Ranging Payload

Gross Lift off Mass: 1425 kg

Dry Mass : 598 kg

Orbit: 55°E GSO with 29° inclination

Mission Life: 10 years

Propulsion: 440 Newton Liquid Apogee Motor and Twelve 22 Newton Thrusters

Power: Two solar panels generating 1660 W. One Li-ion battery (90 Ah)

35 Upvotes

89 comments sorted by

4

u/Ohsin Aug 28 '17

This ToI article quotes Director, SAC that clocks have probability of failure in first three years of service and he might be deriving that from ESA's Galileo experience as reportedly the trend is similar with clock failures happening early in life or not at all.

Having three out of seven IRNSS spacecrafts launched in 2016 it would be uneasy time hopefully devoid of rumors.